This team was dependent on me getting those south balcony partitions removed. Their primary task was to redo all the roof rafters to the calculated specification. However, they were a hold up for AAA as he had to look to securing the new cantilevered beams to the facia. This hold-up simply meant AAA spent some time on their long list of other tasks. This influenced their first task was to strip the old facia down to the good wood underneath as they could while staying a little ahead of the SW-Team with the new rafter work. The facia had taken a real beating over the years as the slight roof tilt washed the drainage over and through the built-out nature of the first facia. So, when they were ahead of the SW-Team, they worked on the new facia and initially focus removal to allow AAA to move ahead with the beams. The north window wall was a filler task for them.
FaciaThe rotted sections of the facia, where water had flown over and through, were removed back to good wood by the NW-Team. In many places like most of the north facia, it had to be replaced completely. This process did uncover steel plates built into the facia at the wing tips which proved very handy for eventually welding the south ends of the cantilevered steel beams. The facia was particularly bad where the water flowed between the outer facia board and the inner edge board which was attached along the ends of the rafters. With the slope (slight) to the north and south over the wing tips, these were the worst areas. They were completely replaced as needed.
In this photo you can clearly see the rough state of the facia on the south side of the house. One can see on the closest wing tip that there is accelerated rot. This is since the gradual roof slope designed to drain the roof of the north crescent did not work entirely as the wing tips sagged. This led a fair amount of run-off to go over and through these areas.
As we look at this mid-point of work on the north crescent, we can see the severe damage even after removal of the outer facia boards. In most places, new inner facia boards were secured to the ends of the new roof rafter system followed by the new cedar outer facia.
It was a pleasure to see the various portions come back together after ripping almost every area apart. In this shot we can see the new cedar boards used for the new facia and the tied in steel beam now holding the wing tips up as originally designed.
I chose this final section because earlier I showed its horrible condition. This section of the north crescent shows the two new windows in the new north window wall for the master bedroom. It also shows the roof flashings (flashings and facia raised to take account of new insulation roof edge to edge) with scuppers added to take run-off past facia to make this go forward with less trouble. Below the snow there is the concrete top of what we used as a shop and what is currently used as the everyday entry point. The door is midway through the tunnel on the right. Rafter Restructuring
Let’s talk the about house circles within circles for a second as it has merits to geometry of the house structure. The tower and the pools were intersecting circles enhancing the design as mentioned in discussions of the effort to replace the pools with a better set of plumbing options. However, the main circle of the house’s paired circumference (is a third of a donut) had a virtual center in the sunken garden with the house sitting back from there as an arc which covered about one third of a circle. The sunken garden was a partial circle balancing the house curvature. The house is designed with 4 arcs. They are the two windows walls and the north and south roof edges. The rafters ran along radii of the virtual circle.
Here is what we had before we started the restoration. Roof edge to roof edge we had a single 2x6. Down supports for both window walls were a single 2x6. The internal roof rafters were a composite with a 1x12 sandwiched to each side of a 2x6.
Here is what was required. Roof edge to edge to be a composite of the 2x6, two 1x12s and two new 2x12s internally (notched to match 6 in rafters on the outside 2x6, two new 1x6s and two new 2x6s). The south windows walls main supports are now a double 2x6 and the north window wall supports now match the new roof rafter composite.
As we go you will see that doing this made it good that I had already figured to totally replace both the south and the north window walls.
This photo gives an inkling to how long the outer boards in the new composite rafters were. According to the plans drawn up for my work, each notched 2x12 was 26.5 feet long. The north roof overhang was notched to match the 6-inch beam height at that location was 3.5 feet wide. The south overhang was longer, again notched to match the 6-inch composite beam there was 5 feet wide.
This photo gives an idea to the massive size of these new rafter composite boards. You can also see the travel from east to west as the NW-Team was doing the raftering, the SW-Team was ripping out the old window wall and placing the new double 2x6 support beams internal to the new wall. In talking about the overall progress at this point, the new radiant floor is in and the two window walls are coming out as the required restructuring to meet code was done.
Working with these new 2x12 members was far easier on the north side. The berm came up high enough that the team could stand there to handle the roof edge. The low ceilings and the solid balcony floor made positioning possible. When they needed to press these members into place, they could use a small hydraulic jack. You will notice in this shot where they have a new 1x6 off the internal 1x12 before adding the outer layer to the new composite.
The south side work was far more difficult. There was just barely enough width of the front walk outside the south window wall to have scaffolding to work with. When they had to press the new composite boards into position, they had to jack from the radiant floor up with long 2x6s. Also in this photo, you can see the temporary roof supports in the forefront getting set to allow the next section of old wall to come out. In the above photo, you can see that as the new rafter composites are completed, they then placed the new wall upper headers.
North Window Wall
Their north window wall task was straight-forward. Measurements were made for two triple pane windows and one triple pane awning window per three roof segments approximately. I was so happy to fix the back window wall in both getting out of the screw on storm windows, but also the impossibility of closing them when they were open. The ease of using them was highly appreciated by me. Hinging them at the top as awning windows both helped the weight close them, but also when the wind whipped up the north berm, the windows guided the air into the house. The new triple panes went everywhere except the solar south wall and were a significant energy savings. Triple panes on the solar wall would have added one more reflection plane and cut the solar gain.
This is a good shot of the old composite beam and the original down support for the north roof and therefore the framework for the old window wall. Plus note part of the facia hanging down. As mentioned in other places the composite roof rafter was a 2x6 sandwiched by two 1x12s.
Here we have the new roof structure in place and the definition of where the north window wall gets positioned. In the forefront are two of the rods used to suspend the entire balcony from the roof. There were notches left in the north stonework when it was built to contain the composite rafters which defined the structure of the balcony thus only requiring additional support out towards the front of balcony.
Custom windows of both awning and non-opening went easily into place. It was a joy after all those years to have insulated windows and ones operated in a normal manner. You’ll also notice at this point as I was getting ready to replace upstairs partitions that the old and no longer useful fin radiators were still in place. As I mentioned, AAA (Gary) had a long list and got to things in the needed order. The fin radiators would no longer be useful due to our being able to drop the floor temperature from close to 200 to 140. These came out as we needed to add ductwork to this same area which I enclosed in the north wall credenza.
We stained the outside to match the weathered overhang. Both images give you the feel for the curvature of the house.
|