The Plan

 

Financials

 

Covering 18% Interest

 

The entire time I owned the house from this first major work, through unexpected major failures and things like the septic bubbling out of the ground by the studio left me feeling that I was juggling raw eggs much of the time.

 

Let’s just say it was a family project and that helped some. My father gave up a large second mortgage in his name, my mother and my stepfather, Richard Hartshorne, loaned me funds, my siblings emotionally supported my efforts, and the banks were friendly.

 

I knew I could do an approved restoration with my knowledge of the house’s needs without spending high architectural costs by working with Taliesin (The Frank Lloyd Wright Foundation and school). I knew what the house needed. When I was done, the restoration was quickly approved as I expected. Madison gave me an Orchid Award and Dane County gave me one of the first Historic Preservation Awards ever. I had saved what is now a National Treasure and a very world-famous Frank Lloyd Wright design.

I bought the property and then planned the work needed. The review of the Department of the Interiors approval application, doing the needed repairs, and securing the approval of the restoration led to the initial first round financing costs of around $53,000.

 

1982 Costs

 

Let’s just say it was and expensive undertaking. Money at that time was costing 18%. I did get about $25,000 for a restoration tax credit. I walked away with no financial gain. That is not to say there was no gain. As I display a few of the photos from my Wisconsin departure in 2019, you’ll see the real gain was knowing I saved an incredible piece of architecture. It was good I had income from my recent computer science degree. All those years,1982-1989, my entire income flowed into the property.

 

Structural Dependencies (The Snake Eating Its Tail Issue)

 

The radiant floor provided support for the south window wall. The south window wall supported the roof. The balcony was suspended from rods which were bolted to some of the roof rafters.

 

Breaking the Circle

 

Wen left about a foot of the old radiant floor under the window wall to be the footing for the new window wall. This had the footing anchored between the outside stone walkway and the new radiant floor before we moved on to start the window wall replacement. The new floor re-attached this section when it was poured.

With that decision, the phases for the project were determined.

 

Plan I followed for the Restoration

My goal for the restoration work, since it would never be possible to be at the point of doing the “while we are at it why don’t we”, was to do as much as possible as it was put back together. If this were a normal house, it would have been equivalent to taking the entire house down to the studs (inside and out).  As I have mentioned, I had extensive experience with many variations of living within this piece of art. This was the time to enhance its potential functioning to a new level, so I did. What made the list was very enforced by the code changes needed to get the work approved and gross level problems like no heat.

 

·       Radiant Floor (20% house heat loss): The new radiant floor is not only be efficient but is also the original nice red that had always been planned.

·       Windows (40% house heat loss): Except for the south solar wall, which is dual pane, all other glass in the house is modern triple pane. (Triple pane in the solar wall would have vastly reduced the solar gain by providing another reflection layer)

·       Roof (20% house heat loss): Several layers of flat roof insulation sheets were added.

·       Skylights: The two existing skylights (bathroom and stairs were rebuilt).

·       Light: The upstairs was brightened by the additions of five new skylights and a smart reshuffling of the upstairs partitions.

·       Pools: New inside pool has usable plumbing if desired to be a water pool.

·       Doors and Windows: Functionality moved from difficult to pleasant.

·       Electrical: Most was redone in the wiring defined by the radiant floor. Most of the downstairs wiring came out with the radiant floor. Much of the upstairs wiring was replaced west of the tower (4/5ths of the balcony) while interconnecting first-floor ceiling box lights

·       Kitchen: The crude cabinets got modern replacements and moved from dark plywood doors to birch while preserving the original pine counter.

·       Bathroom: The tub moved from a back dark corner to a tub/shower enclosure under the newly rebuilt skylight.

·       Cooling: A high efficiency furnace/AC replaced the no longer functional fin radiators along the berm back wall of the upstairs. The new low floor temperature made the old fin system ineffective. This supplements the slower radiant floor and added AC for the increasingly warmer summers.

 

 

 

 

Summary

 

As I mentioned, if this were a normal house, we would have been down to the studs internally and externally. With the stone superstructure (untouched) of this house we started with a gravel floor sub-bed, the balcony front and floor framework, and the original roof rafters and sheeting. The majority of the plumbing and electrical were replaced as well. By any definition, this was a massive project.