Ready Set Go

 

21-ReadyKitchen

Everything had to go to install the new radiant floor. Note here the shadows and light in the kitchen. It is a perfect example of my comments on how the limestone walls, which wrapped the house for part of the south wall cast darkness into both ends of the house on both floors. The light here is from a late day sun which has already moved far west. Only then did sun get into the eastern two spaces. Similarly, only in the first light did sun get into the two west spaces.

 

20-EmptyPreRestoration

Can you say empty? How else are you supposed to replace the floor? Even the grand piano had to go Note the rear white areas where the cold pipes in the summer tended to condense humidity. You can tell this was spring as in the summer, the overhang had the sun skirt just outside of the window wall.

 

Division of labor

This is a good point to add a note about where I got my professional help. I have long since misplaced, either on purpose or by mistake, the results of my lawsuit about their alleged construction management failures. I met him through a friend and the fellow was experienced in the remodeling and restoration processes and had several advanced graduate degrees to boot. I did no cross checking and suffered rework later to two major parts of the restoration. I only mention this here because should you choose to take on a task like this, be very thorough.

 

Check references and previous work!

 

Acquired Experts

 

Architectural

I had been confident that I did not need to use Wright’s architectural design school for plans. It was always in my plan to offset this very expensive project by securing an “approved” restoration and being eligible for the restoration tax credit. I did qualify.  I still had needed an architect to produce plans. Engineering was an expected concern considering the sagging wing tips of the roof and the fact that the roof had never had to hold a snow load (it simply melted it). I also took advantage of my owner status to have Wright’s plans for the house from 1982 until just before I moved back home to Massachusetts in 2019.

 

The projects had three major full-time teams: two carpentry and one plumbing and HVAC. Additionally, the project had folks for concrete, electrical, roofing and me. This was the task breakdown.

 

Three Full Time Teams

 

South Wall Team (SW-Team)

·       Remove and replace the south window wall

 

North Wall Team (NW-Team)

·       Remove and replace north window wall

·       Upgrade roof rafters and north wall infrastructure

·       Rebuild facia as needed

·       Replace slot windows

·       Rebuild two existing skylights and add five more

AAArmadillo (AAA)

·       Radiant floor configuration and installation

·       Pool plumbing

·       Mechanical room (connect radiant floor, pools: heater, pump, and filter)

·       Install steel cantilever beams to lift wing tips

·       Remove old upstairs baseboard plumbing

·       Install auxiliary HVAC for secondary heat and house AC

·       Minor kitchen and bathroom changes.

 

Single Task Teams

 

Electrician

·       Replace radiant floor based electrical outlets in floor and along north wall and tower.

 

Steel Forms (SForms)

·       Remove broken radiant floor

·       Pour and color new floor/pool(color)

·       Install added wall and insulation between pools(color)

·       Pour inside pool bottom and bench

 

Nelson Roofing (NRoofing)

·       Strip roof back exposing wing tip areas (early summer)

·       Strip the rest and apply roof insulation and new tar/pea gravel roof (late Fall)

 

Me

·       Remove and replace east planter

·       Solve long-time floor color problem

·       Work on south wall curtain solution

·       Dismantle upstairs

·       Rebuild upstairs including credenza to hide power and HVAC run

·       Secure new cabinets for the kitchen and refinish the counter

·       Finance the project

 

 

 

 

Mandates

Engineering determinations required bringing the house up to code. This was particularly important with a large almost flat roof in snow country.

 

We Begin

 

I Own a Frank Lloyd Wright House

 

Since I had moved into a restored and for rent farmhouse, when it sold quickly, I had needed a place to sleep and found a trailer I could use for the duration of the project. This suddenness was what created this project I had not thought about.

 

16-IOwnFLWHouse

Sounds better than it was.

 

The FLW Tile

Despite the various issues that the Jacobs had during construction with Mr. Wright, he still blessed the house with his signature tile. Wright was not involved in the project which Herb Jacobs managed on his own. I too have had flak from some of the Jacobs children for the changes I made while restoring this piece of our heritage and art. All I can say is that it took almost no time to get the Department of the Interior to approve the restoration. In 1984 I was also granted a Dane County Historical Preservation Award and the city of Madison granted me an Orchid Award (some got Onions) for a much-appreciated project.

 

 

Floor preparation

 

The house had to be completely empty on the main floor. This meant all the appliances, kitchen counters, tower built-in, back wall living area built in, crude sitting area on the west end (my old TV watching place), the octagon tables, dining table and various designed chairs had to be stored. I also got at this point to filter what I had brought with me (not much). Everything sitting on the radiant floor was removed.  (See Ready Set Go)